UPDATE 12PM:  The upgrade process has come to a point we can move forward.  We'll be opening the systems back up soon.  The vendor is reviewing to see why the process took so long and create a plan to complete the next step at some point in the future.


UPDATE 8AM Wednesday:  The update process is moving much slower than projected.  We are working with the vendor to determine if there are alternatives.  We are also working on a Plan B to bring the clusters up without Panasas, if need be.


UPDATE 5PM:  The Panasas storage update is taking longer than the vendor anticipated.  Systems need to remain offline until this update is completed.  



Date of downtime: Tuesday, February 22, 2022


Approximate time of outage: 7am-5pm


Resources affected by downtime:

UB-HPC cluster (all partitions) 

Industry cluster (all partitions )

Faculty cluster (all partitions)

Portals: WebMO, OnDemand


What will be done:  

  • Operating system updates and reboot of all cluster nodes, front-end login nodes (vortex1/2, transfer) and OnDemand
  • Panasas software update
  • Vast storage software update
  • Infrastructure server updates and reboots


Jobs will be held in queue during the maintenance downtime and will run after the updates are complete.  